Home Page Alert

◄ Back
July 15, 2022 12:00 PM

Read Street Water Main Replacement Project

The replacement of the water main on Read Street from West Street to County Street will begin in the spring of 2021. The exact start date has not yet been determined, but all updates of the project will be posted here once the project begins. This necessary project may cause temporary changes to traffic on that section of Read Street, as well as interruptions of water service to homes on that section of Read Street, as well as all connected side streets in that area, Service interruptions are expected to be minimal.

Facebook Twitter Email

Latest Update:

August 21, 2023 3:26 PM

August 21, 2023- The bid opening for the final paving of Read Street from County Street to West Street is in late August. We expect the paving to complete around Halloween. If this schedule changes, this site will be updated.

Prior Updates

View All Updates
July 14, 2022 11:16 AM

July 14, 2022- Final paving was expected to be complete by early summer 2022. However, installation of new sidewalks has been approved. This installation will likely be completed this fall. Final paving cannot take place until after the sidewalk installation, so will be delayed until later summer to fall 2023.

December 29, 2021 9:17 AM

December 29, 2021- Water main installation is complete, and the new main is in service. Final paving will be completed in the spring 2022.