Neighborhood Impact 

  • Steel deliveries
  • Trucking of loam off site
  • Concrete trucks
  • Construction lights on 4th floor of building
  • Work at Highland Park

 

 

Week of 5/11/2020:

 

  • Steel deliveries and erection
  • Slab on deck concrete pour – Area C 4th floor and Area A roof (5/14 – 6:30am start)
  • Underground plumbing in Area F
  • Trucking loam off site
  • Install CMU shaft at Stair C11 & F12
  • Install roof blocking in Area C
  • Underground utilities within site fence
  • Roofing deliveries
  • Punch list items at Highland Park (weather dependent)