Attleboro High School Project Weekly Update

Below are the projected work activities for this week, provided by Consigli.


Neighborhood Impact 

  • Concrete trucks
  • Generators for temp heaters
  • Steel deliveries

 

 

Week of 3/2/2020:

 

  • Layout/form/rebar/pour footings and walls in Area D and J
  • Steel deliveries and erection
  • Underground electrical and plumbing in Area G and H


Facebook Twitter Email

Other News in Home

Curbside Yard Waste Collection

Posted on: April 2, 2020

Compost Center is Closed

Posted on: April 1, 2020

Special City Council Meeting

Posted on: April 1, 2020

Rubbish Collection

Posted on: March 26, 2020

City Wide Paving Projects

Posted on: March 27, 2020

Meals To Go

Posted on: March 20, 2020

Disposable Wipes

Posted on: March 17, 2020

Update on Government Operations

Posted on: March 16, 2020

Attleboro Rabies Clinic

Posted on: March 16, 2020

2019 Yearly Operational Plan

Posted on: May 20, 2019

HIGHLAND PARK FUTURE USE REPORT

Posted on: February 20, 2019

Tax Exemption Information

Posted on: May 29, 2018

Debt Exclusion Calculation

Posted on: April 18, 2018