Posted on: July 16, 2019

Attleboro High School Project Weekly Update

A message from Consigli Construction today, September 13, 2019:

Our street sweeper broke down this morning, a local contractor has been hired and will be here at 7pm to street sweep Rome Blvd and Rathbun Willard Drive. We have added a rubble strip at site entrance to help mitigate the amount of dirt being tracked out onto the roadways. The street sweeper will be on site next week as needed.

Weekly update from Consigli Construction:

Week of 9/9/19 

  • Complete new breaching outside boiler room
  • Install temp generator to run emergency generator and electrical cabinet at sewer pump station
  • Strip and stockpile gravel at old parking lot
  • Strip and remove loam at old fields
  • Complete the ejector pump in pool mechanical room
  • Hydroseed loamed areas
  • Install new emergency egress door and hardware at loading dock emergency exit
  • Brick up opening at breaching
  • Install manhole covers along Rathbun Willard Dr






Facebook Twitter Email

Other News in Home

New Attleboro High School Ground Breaking

Posted on: September 3, 2019

Resurfacing Notice FY2020

Posted on: June 4, 2019

2019 Yearly Operational Plan

Posted on: May 20, 2019

HIGHLAND PARK FUTURE USE REPORT

Posted on: February 20, 2019

Tax Exemption Information

Posted on: May 29, 2018

Debt Exclusion Calculation

Posted on: April 18, 2018