Attleboro High School Project Weekly Update

Neighborhood Impact 

  • Concrete trucks
  • Site trucking – delivery and removal of soil
  • Site trucking to Highland Park
  • Utility pole wire relocation
  • Generators for temp heaters
  • Paving new sidewalks at Rome Blvd

 Week of 11/18/2019:

 

  • Excavate for new building footings
  • Remove topsoil from site
  • Import structural fill at foundations
  • Transfer services to the new utility poles (National Grid and others)
  • Layout/form/rebar/pour footings and walls in Area B, A, F, G and H
  • Grading and drainage piping at Highland Park
  • Install electrical duct banks to high voltage poles
  • Pave new sidewalks along Rome Blvd
  • Potential work Saturday to connect new sewer lines to the existing lines near Brennan

Facebook Twitter Email

Other News in Home

Winter Parking Ban

Posted on: November 5, 2019

Fall Yard Waste Curbside Collection

Posted on: October 25, 2019

Resurfacing Notice FY2020

Posted on: June 4, 2019

2019 Yearly Operational Plan

Posted on: May 20, 2019

HIGHLAND PARK FUTURE USE REPORT

Posted on: February 20, 2019

Tax Exemption Information

Posted on: May 29, 2018

Debt Exclusion Calculation

Posted on: April 18, 2018