November 2, 2020 8:45 AM

Steere Street Water Main Replacement

AD Paolini is under contract with the Attleboro Water Department to replace the water main on Steere Street. This project is expected to take place throughout the fall. Weekly updates will be provided here. If you have questions or concerns about the project, please contact AD Paolini at 617-999-9799.

Week of November 2, 2020- The contractor will be working from house #312 to house #230, which will require closure of Steere Street to through traffic.

Facebook Twitter Email

Latest Update:

April 7, 2021 9:20 PM

Temporary paving of Steere Street will begin on Thursday, April 8. No closure of the road is expected, but there could be slight delays for passing vehicles.

Prior Updates

View All Updates
April 5, 2021 9:39 AM

Paving for this project will begin within the next two weeks.

February 8, 2021 11:45 AM

The main installation is complete on Steere Street. The contractor will be returning in the spring to complete final paving. In the meantime, please contact the Water Department at 774-203-1854 if there are any issues noted with the temporary paving.