November 2, 2020 8:45 AM

Steere Street Water Main Replacement

AD Paolini is under contract with the Attleboro Water Department to replace the water main on Steere Street. This project is expected to take place throughout the fall. Weekly updates will be provided here. If you have questions or concerns about the project, please contact AD Paolini at 617-999-9799.

Week of November 2, 2020- The contractor will be working from house #312 to house #230, which will require closure of Steere Street to through traffic.

Facebook Twitter Email

Latest Update:

October 20, 2021 1:22 PM

October 20, 2021- Milling of Steere Street is taking longer than expected, so final paving will take place the week of October 25 rather than this week. Full closure of the road is not expected. however lane closures will occur through the end of nextweek on Steere Street.

Prior Updates

September 24, 2021 9:26 AM

September 24, 2021-

Final paving of Steere Street is expected to be completed in mid-October, weather permitting. Milling will be done the week of October 12, with final paving done the following week. Road closures are not expected at this time. However, Steere Street will have one lane closed much of the time during those two weeks.

July 20, 2021 8:43 AM

July 20, 2021- Final paving of Steere Street is expected in late September to early October 2021.

April 7, 2021 9:20 PM

Temporary paving of Steere Street will begin on Thursday, April 8. No closure of the road is expected, but there could be slight delays for passing vehicles.

April 5, 2021 9:39 AM

Paving for this project will begin within the next two weeks.

February 8, 2021 11:45 AM

The main installation is complete on Steere Street. The contractor will be returning in the spring to complete final paving. In the meantime, please contact the Water Department at 774-203-1854 if there are any issues noted with the temporary paving.

January 12, 2021 12:12 PM

Thursday, January 14, 2021- The final tie in and blowoff removal will take place for the Steere Street Project. This will require a water shutoff to Steere Street and associated side streets.

December 31, 2020 10:27 AM

January 4, 2021- The existing water main on Preservation Way will be tied into the new main on Steere Street.

January 5, 2021- the existing water main on Virginia Meadows Drive will be tied into the new main on Steere Street.

Both tie-ins will require the water to be shut off to the residents of both these streets and the adjacent areas of Steere Street.

December 28, 2020 3:23 PM

December 30, 2020- The water mains on Homestead Lane and Settler's Hill Road will be tied into the new water main. the water will be shut down from Pike Avenue to Preservation Way.

December 7, 2020 8:22 AM

Week of December 7- Water main replacement will continue from house #24 to house #100. Service tie-ins will continue from the Pike Avenue end of Steere Street.

November 30, 2020 9:31 AM

Week of November 30- Main replacement will continue from Virginia Meadows Drive to the area of #70 Steere Street. Water service tie-ins will begin from Pike Avenue to Virginia Meadows Drive.

November 6, 2020 2:02 PM

Week of November 9- The contractor will be working in the are of #300 to #200 Steere Street, and tying in to Pike Avenue Thursday or Friday. Road closures are expected throughout the week, and water service is likely to be interrupted to the Pike Avenue end of Steere Street for the tie in. Affected residents will be notified in advance. No work will take place on Wednesday.